Rt 206 Doctors Way to Valley Road project

Hillsborough, Somerset County
Last Update: February 27, 2025

Rt 206 is being widened to two travel lanes in each direction within the project limits beginning south of the Doctors Way intersection (Milepost 66.36) and ending approximately one half mile north of the Valley Road intersection (Milepost 68.00).

Scheduled Completion: Fall 2026


Project Details

The $42 million contract includes construction of multiple operational, safety and state-of-good-repair improvements for all highway users.

  • Widening the highway to two travel lanes in each direction, divided by a center median concrete barrier
  • Constructing jughandles for U-Turn movements at Triangle Road, Valley Road, and near Camplain Road
  • Realigning the highway throughout the project limits
  • Re-grading Falcon Road to match new grades of Rt 206. Falcon Road will be temporarily closed and detoured. The detour will utilize Opie Road and will not affect traffic on Route 206.
  • Replacing a culvert on Route 206 near Valley Road and building a new bridge over a tributary to Royce Brook to connect Valley Road to Route 206
  • Creating drainage basins within the new jughandles and at other locations
  • Upgrading lighting throughout the project limits
  • Upgrading traffic and pedestrian signals throughout the project limits
  • Building a noise wall (completed) along Rt 206 southbound between Farm Road and Doctors Way


View of Valley Road Bridge.  The East Abutment and Pier have been constructed along with the bearings
Work in Progress

View of Valley Road Bridge. The East Abutment and Pier have been constructed along with the bearings.





Southern view of constructed curb and inlet.
Work in Progress

Southern view of constructed curb and inlet.




Northern view of new median barrier
Work in Progress

Northern view of new median barrier.




Project Milestones

Construction Activity Status Estimated Start/Finish
Noise Wall Complete Finished : May 2022
Jughandles In Progress Finish: Summer 2025
Culvert & Bridge replacement In Progress Finish: Summer 2025
Drainage system In Progress Finish: Fall 2025
Curb and Sidewalk In Progress Finish: Fall 2025
Stage 1: widening northbound side of Rt 206 In Progress Finish: Fall 2025
Upgraded traffic & pedestrian signals Not Yet Started Finish : Fall 2025
Regrading Falcon Road Not Yet Started Start: Spring 2025
Upgraded Lighting Not Yet Started Start: Spring 2025
Stage 2: widening southbound side of Rt 206 Not Yet Started Start: Fall 2025
Stage 3: median barrier and final paving Not Yet Started Start: Spring 2026
Project completion In Progress Finish: Fall 2026




Construction of jughandles
Project location map

Google Earth

Last updated date: February 27, 2025 1:19 PM