Construction
Staging
Stage One
- The three through lanes
on Route 440 southbound
will be shifted to the right
using the outside shoulder
as a through lane.
- The left lane of Route
440 northbound will be
shifted to the southbound
roadway using a temporary
crossover through the
median.
- The crossover lane will
continue to carry northbound
traffic and be separated
from southbound traffic
by a concrete median.
The two remaining through
lanes on the Route 440
northbound roadway will
be shifted to the left
or inside of the bridge.
Once the travel lanes
are shifted, the rightmost
or outside portion of
the bridge deck and girders
will be removed and the
new sections of the superstructure
will be lifted into place.
- Three through lanes
will be maintained for
northbound and southbound
traffic.
- The exit ramp from Route
440 northbound to Woodbridge
Avenue (County Route 514)
westbound will be closed
for nine (9) days, from
Friday, June 4 at 10 pm
to Monday, June 14, 2010
at 5 am.
Stage
Two
- The left lane of Route
440 northbound will use
the crossover lane on
the southbound side of
Route 440.
- The two through lanes
maintained on the Route
440 northbound side of
the roadway will be shifted
to the newly reconstructed
(right side) of the bridge.
- Three through lanes
will be maintained for
northbound and southbound
traffic.
- The exit ramp from Route
440 northbound to Woodbridge
Avenue (County Route 514)
westbound will be open
to traffic except the
weekend beginning Friday,
June 18 at 10 pm to Monday,
June 21, 2010 at 5 am.
- The ramps under Route
440 northbound which include
ramps from Route 440 southbound,
Woodbridge Avenue (County
Route 514) eastbound and
westbound and the New
Jersey Turnpike Toll Plaza
departure ramp that leads
to Woodbridge Avenue (County
Route 514) westbound or
the New Jersey Turnpike
Toll Plaza reentry (U-turn)
will be closed for a three
(3) hour period each week
night during construction.
- Additionally, these
ramps are permitted to
be closed between 11 pm
and 8 am on weekends.
|
|